To: Governance and Audit Committee
22nd September 2021
Internal Audit Update
Head of Audit and Risk Management
1 Purpose of Report
1.1 This report presents the update on progress on the annual Internal Audit Plan.
2 Recommendations
2.1 To note the update on progress on the Internal Audit Plan for 2021/22.
3 Reasons for Recommendations
3.1 To ensure the Council complies with statutory requirements for internal audit.
4 Alternative Options Considered
4.1 There are no alternatives.
5 Supporting Information
Internal Audit
5.1 Delivery of the Council’s internal audit services in 2021/22 is being delivered as follows:
· TIAA Ltd who will undertake IT audit;
· Farsight Consulting who will audit schools,
· Wokingham Council’s Business Assurance team delivering internal under services under a S113 agreement;
· One temporary senior auditor working who has been with us since July 2020 and leaves us in early September; and
· two permanent in-house senior auditors who joined us in the summer of 2021.
5.2 Progress against the 2021/22 Internal Audit Plan is set out in Appendix 1. There has been some delay in progressing the 21/22 Audit Plan as a backlog of 20/21 audits deferred to late qtr 4 or early qtr 1 of 21/22 at management request had first to be cleared, schools scheduled to be audited were not prepared to have audits undertaken until the autumn and the new senior auditors were not able to join us until July and August.
6 Consultation and Other Considerations
Legal Advice
6.1 There are no specific legal implications arising from the recommendations in this Report.
Financial Advice
6.2 There are no financial implications arising from this report.
Equalities Impact Assessment
6.3 Not applicable.
Strategic Risk Management Issues
6.4 A robust internal audit service is essential for ensuring proper processes are in place for effective control.
Background Papers
Internal Audit Plan 2021/22
Internal Audit Charter
Contact for further information
Sally Hendrick, Head of Audit and Risk Management - 01344 352092
Sally Hendrick
Head of Audit and Risk Management
Sally.hendrick@bracknell-forest.gov.uk
01344 352092
1.1 The Council is required under the Accounts and Audit (Amendment) (England) Regulations to “maintain an adequate and effective system of internal audit of its accounting records and of its systems of internal control in accordance with the proper practices in relation to internal control.” This report summarises the activities of Internal Audit for the period April to 31st August 2021 drawing together progress on the Annual Internal Audit Plan, risk management and other activities carried out by Internal Audit.
2.1 The basic approach adopted by Internal Audit falls broadly into four types of audit:
· System reviews provide assurance that the system of control in all activities undertaken by the Council is appropriate and adequately protects the Council’s interests.
· Regularity (financial) checking helps ensure that the accounts maintained by the Council accurately reflect the business transacted during the year. It also contributes directly towards the external auditor’s audit of the annual accounts.
· Computer/IT audits, carried out by specialist audit staff, provide assurance that an adequate level of control exists over the provision and use of computing facilities
· Certification as required by relevant Government departments that grant monies have been spent in accordance with grant terms and conditions.
2.2 Recommendations are made after individual audits, leading to an overall assurance opinion for the system or establishment under review and building into an overall annual assurance opinion on the Council’s operations called the Head of Internal Audit Annual Opinion. The different categories of recommendation and assurance opinions are set out in the following tables.
2.3 Since 1st April 2019 we have been categorising our audit opinions according to our assessment of the controls in place and the level of compliance with these controls as follows::
|
Good - There is a sound system of internal control designed to achieve the objectives of the system/process and manage the risks to the achievement of objectives and this is being complied with. Recommendations will only be of low priority. |
|
Adequate - there is basically a sound system of control but there are some areas of minor weakness and/or some areas of non- compliance which put the system/process objectives at risk. Recommendations will only be low or moderate in priority. |
|
Partial - there are areas of weakness and/or non- compliance with control which put the system/process objectives at risk and undermine the system’s overall integrity. Recommendations may include major recommendations but could only include critical priority recommendations if mitigated by significant strengths elsewhere. |
|
Inadequate - controls are weak across a number areas of the control environment and/or not complied with putting the system/process objectives at significant risk. Recommendations will include major and/or critical recommendations |
|
None - There is no control framework in place and management is inadequate leaving the system open to risk of significant error or fraud. |
2.4 We categorise our recommendations according to their level of priority as set out below:
|
Critical - Critical and urgent in that failure to address the risk could lead to factors such as significant financial loss, significant fraud, serious safeguarding breach, critical loss of service, critical information loss, failure of major projects, intense political or media scrutiny. Remedial action must be taken immediately. |
|
Major - failure to address issues identified by the audit could have significant impact such as high financial loss, safeguarding breach, significant disruption to services, major information loss, significant reputational damage or adverse scrutiny by external agencies. Remedial action to be taken urgently. |
|
Moderate - failure to address issues identified by the audit could lead to moderate risk factors materialising such as medium financial loss, fraud, short term disruption to non-core activities, scrutiny by internal committees, limited reputational damage from unfavourable media coverage. Prompt specific remedial should be taken. |
|
Low - failure to address issues identified by the audit could lead to low level risks materialising such as minor errors in system operations or processes, minor delays without impact on service or small financial loss. Remedial action is required. |
3.1 The Annual Internal Audit Plan for 2021/22 was considered and approved by the Governance and Audit Committee on 24th March 2021. The delivery of the individual audits during 2021/22 is being undertaken by
· TIAA Ltd who will undertake IT audit;
· Farsight Consulting who will audit schools,
· Wokingham Council’s Business Assurance team delivering internal under services under a S113 agreement;
· One temporary senior auditor working who has been with us since July 2020 and leaves us in early September; and
· two permanent in-house senior auditors who joined us in the summer of 2021.
3.2 There has been some delay in progressing the 21/22 Audit Plan as a backlog of 20/21 audits deferred to late qtr 4 or early qtr 1 of 21/22 at management request had first to be cleared, schools scheduled to be audited were not prepared to have audits undertaken until the autumn and the new senior auditors were not able to join us until July and August.
3.3 Between April to August 2021, 1 grant audit and 4 reports/memos were finalised, 3 reports/memos were issued in draft awaiting management responses, 5 reports were issued in draft for discussion,1 draft report was at quality review stage and 13 audits were work in progress.
3.4 Details on the status and outcome of all audits are attached at Appendix A. A summary of the outcome of finalised and audits with reports issued in draft are set out below.
2021/22 ASSURANCE LEVELS |
NUMBER OF AUDITS TO DATE |
|
2020/21 ASSURANCE LEVELS |
NUMBER OF AUDITS |
Good |
2 |
|
Good |
4 |
Adequate |
2 |
|
Adequate |
15 |
Partial |
1 |
|
Partial |
10 |
Inadequate |
0 |
|
Inadequate |
0 |
No assurance |
0 |
|
No assurance |
0 |
Total for Audits with an Opinion |
5 |
|
Total for Audits with an Opinion |
29 |
Memos and reports with Major Recommendation and no Opinion |
0 |
|
Memos and reports with Major Recommendation and no Opinion |
4 |
Other Follow Up Memos/ Reports with no Opinion |
2 |
|
Other Follow Up Memos/ Reports with no Opinion |
3 |
Total Audits |
7 |
|
Total Audits |
36 |
Grant Certifications |
1 |
|
Grant Certifications |
7 |
Overall Total |
8 |
|
Overall Total |
43 |
Identified High Priority Control Issues
3.5 Audits which have identified high priority recommendations will generally be revisited in 2022/23, to ensure successful implementation of agreed recommendations. No critical recommendations have been raised to date in 2020/21 however a number of recommendations falling under our major recommendation category have been raised as set out below:
AUDITS WHERE HIGH PRIORITY ISSUES HAVE BEEN IDENTIFIED SINCE THE LAST UPDATE IN THE INTERNAL AUDIT 20/21 ANNUAL REPORT IN JUNE 2021 |
||
· Security camera controls |
Three major recommendations were raised relating to gaps in the CCTV policy and non compliance that should be addressed, ensuring that there is adequate signage at camera locations and setting rules and developing procedures for access and sharing of data.
|
ASSURANCE OPINION: PARTIAL |
Update of Previous Audits with High Priority Recommendations
3.6 Since April 2021, we have followed up one audit from 2020/21 where significant weaknesses had been identified (reactive maintenance). The Head of Audit and Risk Management can report that issues previously identified have been addressed.
Quality Assurance and Improvement Programme
3.7 As shown below, no completed client questionnaires had been received to date for 2021/22. In 92% of cases internal audit delivered the first draft report within 15 days of the exit meeting.
|
Client Questionnaires |
Draft Report /Memo Produced within 15 Days of Exit meeting |
|
|
Received |
Satisfactory |
|
1st April to 31st August 2021 |
- |
- |
92% |
2020/21 |
9 |
89% |
60% |
4.1 It is still too early in the financial year to make a reliable assessment on the direction of travel of the control environment. Progress to improve the control environment will be monitored quarterly based on the outcome of the audits undertaken and in particular identifying whether agreed management actions for areas previously found to have significant control weaknesses have been implemented as this has been a key factor in the Head of Audit and Risk Management’s annual opinion on the control environment for the last 3 years.
5.1 The Strategic Risk Register has already been reviewed twice by the Strategic Risk Management Group (SRMG) and once by the Corporate Management Team. Directorate risk registers continue to be updated quarterly.
APPENDIX 1
2020/21 INTERNAL AUDIT PLAN OUTCOMES NOT PREVIOUSLY REPORTED
*Key indicator- Draft report issued within 15 days of exit meeting
“D”- deferred at management request from 20/21 to 21/22
AUDIT |
Start Date |
Date of Draft Report |
*Key Indicator Met |
Assurance Level |
Recommendation Priority |
Status |
||||||
|
|
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
Security camera controls |
2/3/21 |
20/8/21 |
P |
|
|
P |
|
|
|
3 |
2 |
Finalised |
Parenting Assessments |
11/1/21 |
9/6/21 |
P |
|
|
|
|
|
|
|
|
Out in draft for discussion |
Foster Panels Compliance |
May 2021 |
26/6/21 |
P |
|
P |
|
|
|
|
4 |
2 |
Draft report issued |
Continuing Health Care |
17/3/21 |
2/7/21 |
P |
|
P |
|
|
|
|
4 |
1 |
Draft report issued |
2021/22 INTERNAL AUDIT PLAN
1.GOVERNANCE
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator Met* |
Assurance Level |
Recommendation Priority |
Status |
|||||||||
|
|
|
|
Good |
Adequate |
Partial |
inadequate |
Critical |
Major |
Moderate |
Low |
|
|||
Data indicators |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
|||
Project management of O&S reviews and subsequent action plan implementation |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
|||
|
|
|
|
|
|
|
|
|
|
|
|
“D” Audit deferred to qtr 1 of 22/23 as Business continuity project delayed due to COVID |
|||
Complaints Process |
August 21 |
|
|
|
|
|
|
|
|
|
|
Draft issued for discussion
|
|||
Corporate Governance infrastructure –People only |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
|||
E+ card- general control, IT controls and information governance arrangements with contractors |
|
|
|
|
|
|
|
|
|
|
|
Work in progress |
|||
Grant Reviews and Certifications Bus Service Operator |
|
|
|
|
|
|
|
|
Work in progress |
||||||
Troubled Families |
24/6/21 |
30/6/21 |
P |
N/A – Memo to support PBR submission |
|
|
|
|
Finalised |
||||||
Troubled Families- March 2022 submission |
|
|
|
|
|
|
|
|
Qtr 4 audit |
||||||
Green Homes Grants compliance audit |
|
|
|
|
|
|
|
|
|
|
|
Work in progress |
|||
COVID Restart grants |
|
|
|
|
|
|
|
|
Work in Progress |
||||||
COVID Additional Restrictions grants |
|
|
|
|
|
|
|
|
Work in Progress |
||||||
Pot Hole Fund |
|
|
|
|
|
|
|
|
Work in Progress |
||||||
Local transport capital block funding (integrated transport and highways maintenance) |
|
|
|
|
|
|
|
|
Work in Progress |
||||||
COVID Track and Trace grants |
|
|
|
|
|
|
|
|
Qtr 3 audit |
||||||
2. COUNCIL WIDE
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator Met* |
Assurance Level |
Recommendation Priority |
Status |
||||||
|
|
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
Amazon account |
|
|
|
|
|
|
|
|
|
|
|
|
Climate Change
|
July 2021 |
5/8/21 |
|
|
|
|
|
|
|
|
|
Draft report issued for discussion |
Debt management |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
3. CORE FINANCIAL SYSTEMS
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator Met* |
Assurance Level |
Recommendation Priority |
Status |
||||||
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
||
Reconciliations
|
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Staff establishment costs (Joint HR and Finance audit budgeted under OD, Transformation and HR) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Banking -advisory audit |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Council Tax |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Business Rates |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Creditors |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
Housing Benefit and Council Tax Reduction |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
4. IT AUDIT
Start Date |
Date of Draft Report |
Key Indicator Me* |
Assurance Level |
|
|
|
|
Status |
||||
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
||
Transport routing |
August 2021 |
|
|
|
|
|
|
|
|
|
|
Work in progress |
Emergency Duty Service System |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Forestcare IT systems including telephony |
|
|
|
|
|
|
|
|
|
|
|
Deferred to qtr 4 due to delays on the new system |
Heath and Social Care ICT Care Systems Integration (Dependent upon Digital Strategy) |
|
|
|
|
|
|
|
|
|
|
|
Late Qtr 2 audit |
CORE waste management system |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
|
|
|
|
|
|
|
|
|
|
|
|
Cancelled as not required by service area |
Agresso (Follow up- major recommendations raised in 2019/20 and 2020/21) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Cyber Security – Incident Management and Resilience |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Cyber liability (Follow up- partial assurance 2020/21) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
DSPT NEW AUDIT |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
5. PLACE, PLANNING, AND REGENERATION
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator met |
Assurance Level |
Recommendation priority |
Status |
||||||
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
|||
SANGs |
May 2021 |
16/7/21 |
P |
N/A – Advisory memo |
|
|
|
1 |
“D” Finalised |
|||
S106 – Use of the monies in compliance with development in the relevant geographic area |
|
11/8/21 |
P |
P |
|
|
|
|
|
|
6 |
“D” Draft report issued |
Tree service |
1/9/21 |
|
|
|
|
|
|
|
|
|
|
Work in progress |
Street lighting follow up (partial assurance opinion 2019/20) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
Development Control |
|
|
|
|
|
|
|
|
|
|
|
Work in progress |
Building Control and land charges |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Public Health |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
T
6. CHIEF EXECUTIVE’S OFFICEcosts advisory review
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator met* |
Assurance Level |
Recommendation Priority |
Status |
||||||
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
||
Transformation support costs advisory review w |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
7. DELIVERY
AUDIT |
Start Date |
Date of Draft Report |
Key Indicator met* |
Assurance level |
Recommendation Priority |
Status |
||||||
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
||
Public Protection Partnership (Follow up- partial assurance 2020/21) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Reactive Maintenance (Follow up- partial assurance 2020/21) |
August 2021 |
27/8/21 |
P |
N/A- Follow up memo. All recommendations addressed |
|
|
|
|
Finalised |
|||
Commercial property (Follow up- partial assurance 2020/21) |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Cemetery and Crematorium |
12/7/21 |
|
|
|
|
|
|
|
|
|
|
“D” Draft report being quality reviewed
|
Everyone Active Covid support |
|
30/6/21 |
P |
P |
|
|
|
|
|
|
|
Finalised |
Green Homes Grants |
July 2021 |
31/8/21 |
P |
|
|
|
|
|
|
|
|
Draft report issued for discussion
|
8. PEOPLE
|
Start Date |
Date of Draft Report |
Key Indicator Met* |
Assurance levels |
Recommendation Priority |
Status |
||||||
|
|
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
|
||
Transport in CTPLD- advisory review |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Direct payments- advisory piece on fraud triggers |
|
|
|
|
|
|
|
|
|
|
|
Work in progress |
Financial assessments |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Preparation for new Liberty Safeguard regulations – advisory piece |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Deputyships and appointees |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Commissioning due diligence checks |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Children’s placements |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 4 audit |
Supervision- advisory review covering ASC and Mental Health |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Breakthough follow u(Follow up- partial assurance 2020/21)p |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
|
|
|
|
|
|
|
|
|
|
|
|
Audit cancelled at request of service area |
Permanency planning |
August 2021 |
|
|
|
|
|
|
|
|
|
|
Work in Progress
|
Post leaving Care |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Larchwood |
26/7/21 |
|
|
|
|
|
|
|
|
|
|
Work in Progress
|
Glenfield- mental health supported living |
August 2021 |
|
|
|
|
|
|
|
|
|
|
“D” Work in Progress
|
|
|
|
|
|
|
|
|
|
|
|
|
Cancelled by service area |
Forestcare |
|
|
|
|
|
|
|
|
|
|
|
Late Quarter 2 audit |
Disabled Facilities Grants- |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
Homelessness procurement advisory piece |
|
|
|
|
|
|
|
|
|
|
|
Late Qtr 2 audit |
Housing Management follow up |
|
|
|
|
|
|
|
|
|
|
|
Qtr 4 audit |
COVID Test and trace grants |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Open Learning Centre |
|
|
|
|
|
|
|
|
|
|
|
Late quarter 2 audit |
Nursery provider support payments |
|
|
|
|
|
|
|
|
|
|
|
Deferred to qtr 4 at service area request |
9. SCHOOLS
AUDIT
|
Start Date |
Date of Draft Report |
Key Indicator Met |
Good |
Adequate |
Partial |
Inadequate |
Critical |
Major |
Moderate |
Low |
Status |
|
|
|
|
|
|
|
|
|
|
|
|
|
School census |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Services to schools- Can Do |
12/8/21 |
|
|
|
|
|
|
|
|
|
|
Work in Progress
|
Free school meals |
|
|
|
|
|
|
|
|
|
|
|
Qtr 3 audit |
Fox Hill (follow up -Ltd 2017/18 and 2018/19) |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
The Pines |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Woodenhill (follow up -Ltd 2018/19) |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Ascot heath (reaudit-Ltd 2018/19) |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Sandhurst (follow up partial 19/20) |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Kennel Lane follow up |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
St Michael’s Easthampstead (follow up partial 19/20) |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Whitegrove |
7/6/21 |
29/7/21 |
X |
|
|
|
|
|
|
|
|
“D” Draft for discussion issued |
Binfield |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
St Michael’s Sandhurst |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Winkfield |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
Owlsmoor |
|
|
|
|
|
|
|
|
|
|
|
“D” Qtr 3 audit |
APPENDIX 2
2020/21 AUDITS IDENTIFYING SIGNIFICANT ISSUES |
||
AUDIT |
RATING |
CURRENT AUDIT STATUS |
· Debt Management |
PARTIAL |
To be re-audited in Qtr 4 |
· Management of Essential Car User Allowances and Mileage |
PARTIAL |
To be followed up in Qtr 4 |
· Public Protection Partnership |
PARTIAL |
To be followed up in Qtr 3 |
· Management of Commercial Properties
|
PARTIAL |
To be followed up in Qtr 4 |
· Reactive Maintenance |
PARTIAL |
Followed up and all significant issues raised have been addressed |
· Cyber |
PARTIAL |
To be followed up in Qtr 3 |
· Agresso IT System Follow Up
|
FOLLOW UP HENCE NO OPINION BUT MAJOR RECOMMENDATIONS RAISED |
To be followed up in Qtr 3 |
· Creditors
|
PARTIAL |
To be re-audited in Qtr 4 |
· Business Rates
· Council Tax and council tax |
BOTH PARTIAL
|
To be re-audited in Qtr3 |
· Domiciliary Care Follow up |
FOLLOW UP HENCE NO OPINION BUT MAJOR RECOMMENDATION STILL OUTSTANDING |
To be re-audted in Qtr 1 of 22/23 |
· Breakthrough |
PARTIAL |
To be followed up in Qtr 3 |
OTHER AUDITS AREAS WHERE SIGNIFICANT ISSUES IDENTIFIED PRE 20/21 WERE STILL OUSTANING AT 31/3/21 |
CURRENT AUDIT STATUS |
· Forestcare (Follow Up Memo. 2019/20 Also limited in 2017/18) |
Forestcare will be re-audited at the end of Qtr 2 |
· Adult Social Care Pathway (Qtr 4 2017/18 Audit)
|
To be followed up in Qtr 4 |
· Loans for Housing Rents and Deposits
|
To be followed up as part of the debt management audit in Qtr 4 of 21/22 |
· Public Health
|
To be re-audited in Qtr 4 |
· Disabled Facilities Grants |
To be re-audited in Qtr 3 |
· ICT Continuity Management |
To be re-audited as part of business continuity in Qtr 1 of 22/23 |